Agile Frameworks/Methodologies · Topic 2 of 4

Planning Iterations

CAPM iteration planning: timeboxed iterations, backlog and user stories as scope inputs, turning a WBS into iterations, estimating and adaptive tracking.

  • 3 min
In a nutshell
  • Iterations are fixed timeboxes, usually one to four weeks.
  • Scope lives in the prioritized product backlog.
  • Epic or feature, then user story, then task.

What it is

An iteration is a short, timeboxed cycle of development, typically one to four weeks, in which the team builds a usable piece of the product. Iteration planning decides which backlog items to take on, based on priority and the team's capacity.

Product backlogprioritizedIteration planningselect itemsBuild and testReview with customerRetrospective

How it works

Logical units of iterations

UnitMeaning
ReleaseA set of iterations that delivers a meaningful set of features to users
Iteration or sprintA fixed timebox, the same length each time
Feature or epicA large piece of functionality, split into stories
User storyA small piece of value from the user's point of view
TaskThe technical work the team does to complete a story

Inputs for scope

In adaptive projects, scope is held in the product backlog: an ordered list of everything that might be built. Inputs include the product vision and roadmap, stakeholder needs, user stories, feedback from earlier iterations and lessons learned.

A user story often follows the form: "As a (type of user), I want (goal) so that (benefit)". Good stories follow INVEST: Independent, Negotiable, Valuable, Estimable, Small, Testable.

Translating a WBS into iterations

PredictiveAdaptive equivalent
WBSProduct backlog
DeliverableFeature or epic
Work packageUser story
ActivityTask
ScheduleRelease and iteration plan

A worked example: a WBS has a deliverable "online ordering", with work packages "browse menu", "pay online" and "track order". In an adaptive plan, "online ordering" becomes an epic and each work package becomes one or more user stories ranked in the backlog. The team might deliver "browse menu" in iteration 1 and "pay online" in iteration 2.

Estimating

TechniqueHow it works
Story pointsA relative measure of size and effort, not hours
Planning pokerEach team member reveals an estimate card at once; differences are discussed and the team re-estimates
T-shirt sizingRough sizes: XS, S, M, L, XL
Affinity estimatingGrouping items of similar size

Velocity is the amount of work, usually in story points, a team completes per iteration. It helps forecast how many iterations the remaining backlog needs. Velocity belongs to one team and is not used to compare teams.

Pros and cons of iterations

ProsCons
Frequent feedback and early valueNeeds regular customer involvement
Problems are found earlySome work does not split easily
Easy to change priorities between iterationsTotal scope and end date are less certain up front
Regular rhythm and focusShort timeboxes can feel rushed without good discipline

Adaptive versus predictive tracking

Predictive tracking compares actuals with a fixed baseline. Adaptive tracking measures completed, working increments each iteration and updates forecasts from real velocity. This makes progress visible sooner and gives early warning when the plan must change.

Exam tip

The iteration length stays fixed. If not all work fits, the team reduces scope for that iteration rather than extending the timebox.

How the exam asks about this

  • "What is velocity?" The amount of work a team completes per iteration.
  • "In an adaptive project, what replaces the WBS for scope?" The product backlog.
  • "Which estimation technique has everyone reveal a card at the same time?" Planning poker.

What to remember for the exam

  • Iterations are fixed timeboxes, usually one to four weeks.
  • Scope lives in the prioritized product backlog.
  • Epic or feature, then user story, then task.
  • User stories: "As a ... I want ... so that ..."; INVEST.
  • Story points are relative; velocity is points completed per iteration.
  • Adaptive tracking measures working increments, not percent of plan.
Watch out

Do not extend an iteration to finish work. Unfinished items return to the backlog and are reprioritized.

Common mistakes

Treating story points as hours. They are relative size.

Comparing velocity between teams. Each team's points are different.

Planning every iteration in detail up front. Detail is added just in time.

Check yourself

  • What does INVEST stand for?

    Independent, Negotiable, Valuable, Estimable, Small, Testable.

  • What is the adaptive equivalent of a work package?

    A user story in the product backlog.

  • How is velocity used?

    To forecast how many iterations the remaining backlog will take for that team.

Topic 2 of 4 in Agile Frameworks/Methodologies

Test yourself on Agile Frameworks/Methodologies