PMI CAPM Practice Exam
PMI Certified Associate in Project Management (CAPM)
The PMI Certified Associate in Project Management (CAPM) is PMI's entry-level project management certification. It shows you understand the fundamentals, terminology and processes of effective project management. The exam follows PMI's CAPM examination content outline and is weighted Project Management Fundamentals and Core Concepts 36 percent, Predictive, Plan-Based Methodologies 17 percent, Agile Frameworks/Methodologies 20 percent and Business Analysis Frameworks 27 percent. It has 150 questions in 180 minutes, 15 of them unscored pretest questions. This practice exam uses multiple choice and drag-and-drop matching questions at the same entry level.
Question bank updated : questions, answers, explanations and chapters.
Certification Overview
- Exam name: CAPM
- Vendor: PMI
- Exam code: CAPM
- Duration: 180 minutes
- Total questions: about 150
- Our practice exam pass mark: 70%
Who Should Take This Exam?
Student, Graduate, Project Coordinator, Junior Project Manager, Project Team Member, Business Analyst, PMO Assistant, Team Lead moving into project management
Prerequisites
A secondary degree (high school diploma, GED or global equivalent) and 23 hours of project management education completed before the exam. No project experience is required.
Topics Covered
- Project Management Fundamentals and Core Concepts
- Predictive, Plan-Based Methodologies
- Agile Frameworks/Methodologies
- Business Analysis Frameworks
Question Types
- Multiple Choice (Single Answer)
- Drag and Drop
CAPM Practice Questions
Our question bank contains 1049+ practice questions for this certification. Sample questions from each exam chapter. Expand a question to see the answer choices. With a subscription, you get unlimited practice exams with randomised questions from our full question bank.
Project Management Fundamentals and Core Concepts
What is a project life cycle?
- A. The order in which work packages are approved for funding
- B. The group of processes repeated within every phase
- C. The phases a project moves through from start to finish Correct answer
- D. The stages a product passes through from concept to retirement
Option C is correct because a project life cycle is the series of phases a project passes through from start to finish. Option A is about funding, not phases. Option B describes process groups, not phases. Option D is the product life cycle, which covers the product's whole life including operation and retirement, not just the project.
A team prefers to define scope, schedule and cost up front and then deliver to the plan. Which life cycle type fits this preference?
- A. Predictive Correct answer
- B. Iterative
- C. Incremental
- D. Adaptive
Option A is correct because a predictive (plan-driven) life cycle fixes scope, schedule and cost early and then delivers to that plan. Iterative, incremental and adaptive approaches all expect scope to be refined as work progresses, so they do not match this preference.
The project charter is developed during which process group?
- A. Initiating Correct answer
- B. Executing
- C. Closing
- D. Planning
Option A is correct because the project charter is created in Initiating; it authorizes the project and names the project manager. Planning builds the management plan after authorization, Executing does the work, and Closing finishes the project.
At the end of a phase, a review decides whether the project continues, changes or stops. What is this review called?
- A. Lessons learned session
- B. Change control board meeting
- C. Baseline audit
- D. Phase gate Correct answer
Option D is correct because a phase gate (also called a phase review or kill point) is the end-of-phase decision to continue, change or stop. A lessons learned session captures knowledge, a change control board decides on change requests, and a baseline audit is not a standard phase decision.
A software vendor must deliver a customer portal by a contractually fixed date and budget, yet the user interface requirements are expected to keep changing. Which life cycle approach suits this best?
- A. An adaptive approach with the backlog reprioritized each sprint
- B. A hybrid approach with fixed milestones and iterative build work Correct answer
- C. A predictive approach with the scope baselined at the start
- D. An incremental approach with a release after each completed phase
Option B is correct because the fixed date and budget call for predictive-style milestones, while the changing interface requirements call for iterative build work, which is a hybrid approach. A fully adaptive approach would not respect the fixed commitments, a purely predictive one cannot absorb changing requirements, and releasing after each phase is not what incremental delivery means.
Predictive, Plan-Based Methodologies
Which description fits a predictive, plan-based approach?
- A. Scope, schedule and cost are planned up front Correct answer
- B. Requirements emerge from frequent customer demos
- C. Work items are pulled through a Kanban board
- D. Work is delivered in short timeboxed iterations
Option A is correct because a predictive approach defines scope, schedule and cost in detail at the start and then follows the plan. Options B and D describe agile ways of working (customer demos, short iterations), and option C describes Kanban, which pulls work continuously rather than planning it all up front.
A predictive life cycle is also commonly known as what?
- A. Waterfall Correct answer
- B. Incremental
- C. Iterative
- D. Adaptive
Option A is correct because a predictive life cycle is also called waterfall: phases run in sequence and the plan is set early. Incremental and iterative approaches deliver in pieces or repeat cycles, and adaptive is the term for agile-style approaches, so none of those is another name for predictive.
Predictive approaches suit projects whose requirements are best described as what?
- A. Reprioritized in every iteration
- B. Expected to emerge during delivery
- C. Well understood and stable at the start Correct answer
- D. Shaped by user feedback after each release
Option C is correct because predictive approaches work best when requirements are well understood and stable at the start, so they can be planned in full. Options A, B and D all describe requirements that change or emerge, which is where agile approaches fit better.
Why do industries such as construction and pharmaceuticals often choose a predictive approach?
- A. Short iterations reduce the need for documentation
- B. Phased approvals support regulatory compliance Correct answer
- C. Self-organizing teams decide scope during delivery
- D. Frequent customer reviews keep requirements flexible
Option B is correct because these industries are regulated, and phase-by-phase approvals and documentation help prove compliance. Options A, C and D describe agile traits (light documentation, self-organizing teams, flexible requirements) that do not suit strict regulatory control.
Which organizational setting makes a predictive approach easier to apply?
- A. Formal procedures and documented approvals Correct answer
- B. Teams that set priorities themselves each day
- C. Customers who are on site every day to give feedback
- D. Leaders who favor experiments over written plans
Option A is correct because formal procedures and documented approvals match the structured, plan-driven nature of a predictive approach. Options B, C and D describe self-directed teams, constant customer presence and experimentation, which suit agile settings.
Agile Frameworks/Methodologies
Which condition most favors choosing an adaptive approach?
- A. Scope is fully defined and approved upfront
- B. Requirements will evolve during delivery Correct answer
- C. Regulation requires sign-off at each phase gate
- D. The work repeats the same steps every time
Option B is correct because adaptive approaches are designed for work where requirements are expected to change during delivery, so the team can respond through short feedback cycles. Fully defined upfront scope and identical repeating steps point to a predictive approach, and phase-gate sign-offs are a predictive control.
A startup expects customer feedback to reshape its app features every few weeks. Which approach fits best?
- A. Plan-driven, with phase-gate approvals
- B. Predictive, with a fixed baseline
- C. Adaptive, with short feedback loops Correct answer
- D. Hybrid, with a locked design phase
Option C is correct because frequent customer feedback that reshapes features calls for an adaptive approach with short feedback loops. Plan-driven, predictive and hybrid-with-locked-design options (A, B, D) fix the plan up front and cannot absorb changes every few weeks.
Firmware for a regulated device must meet documented compliance requirements, yet its user interface is still unclear. Which approach fits best?
- A. Fully predictive for the whole product
- B. Fully adaptive with no upfront documents
- C. Hybrid: fixed compliance, iterative interface Correct answer
- D. Predictive interface, adaptive compliance work
Option C is correct because a hybrid approach fits: the documented compliance requirements are stable and suit predictive control, while the unclear user interface benefits from iterative, feedback-driven work. Fully predictive or fully adaptive ignores one of the two needs, and option D reverses which part suits which approach.
What is a key benefit of an adaptive approach when requirements are uncertain?
- A. Early delivery of working increments Correct answer
- B. A fixed scope locked at the start
- C. A detailed full-scope estimate at kickoff
- D. Formal sign-off before each phase
Option A is correct because adaptive approaches deliver working increments early, so the team can learn and adjust when requirements are uncertain. Options B, C and D lock scope, estimates or approvals up front, which suits predictive work with stable requirements.
Which of these is an example of an adaptive approach?
- A. Waterfall
- B. Phase-gate model
- C. Scrum Correct answer
- D. Critical path method
Option C, Scrum, is correct because it is an iterative, adaptive framework that delivers in short sprints. Waterfall and the phase-gate model are predictive, and the critical path method is a scheduling technique rather than a development approach.
Business Analysis Frameworks
What is the primary purpose of business analysis on a project?
- A. Identify needs and recommend solutions Correct answer
- B. Find defects in the delivered product
- C. Sequence activities and track milestones
- D. Approve funding for the project
Option A is correct because business analysis exists to identify business needs and recommend solutions that deliver value. Finding defects is quality work (B), sequencing activities and tracking milestones is schedule management (C), and approving funding is a sponsor or governance decision (D).
Which responsibility belongs to the business analyst rather than the project manager?
- A. Assigning team members to tasks
- B. Reporting schedule variance to the sponsor
- C. Managing the project budget
- D. Eliciting and documenting requirements Correct answer
Option D is correct because eliciting, analyzing and documenting requirements is the core business analysis responsibility. Assigning team members, reporting schedule variance and managing the budget (options A, B and C) are project management duties.
After sales fall, a business analyst finds that slow customer onboarding is the cause and records the problem and the gap to be closed. Which deliverable is this?
- A. Requirements traceability matrix
- B. Needs assessment Correct answer
- C. Stakeholder register
- D. Project charter
Option B is correct because a needs assessment documents the business problem or opportunity and the gap between the current and desired state. A traceability matrix (A) links requirements to deliverables, a stakeholder register (C) lists stakeholders, and a project charter (D) authorizes the project.
Which tool lists stakeholders along with their interest, influence and expectations?
- A. Stakeholder register Correct answer
- B. RACI matrix
- C. Lessons learned register
- D. Issue log
Option A is correct because the stakeholder register records each stakeholder's interest, influence and expectations. A RACI matrix assigns roles, the lessons learned register captures experience, and the issue log tracks problems, so none of those profile stakeholders.
A business analyst must record how often each stakeholder group is updated and in what format. Which document holds these decisions?
- A. Requirements management plan
- B. Stakeholder register
- C. Project charter
- D. Communications management plan Correct answer
Option D is correct because the communications management plan defines who receives which information, how often, and in what format. The requirements management plan (A) covers how requirements are handled, the stakeholder register (B) identifies stakeholders, and the charter (C) authorizes the project.
Free Study Guide
Read the free PMI CAPM study guide: every exam topic explained in plain English, with diagrams, exam tips and the mistakes to avoid.
More PMI Practice Exams
Practise with realistic mock exams to prepare for your PMI certification.