Agile Frameworks/Methodologies · Topic 4 of 4

Adaptive Artifacts and Task Management

CAPM adaptive controls and tasks: backlogs, boards, burndown and burnup charts, Definition of Done, success criteria and prioritizing with MoSCoW.

  • 4 min
In a nutshell
  • Artifacts: product and iteration backlogs, task board, burndown, burnup, cumulative flow, Definition of Done.
  • Burndown: work left; burnup: work done against total scope.
  • Acceptance criteria are per item; the Definition of Done applies to all items.

What it is

Adaptive projects control work through visible artifacts rather than long reports. Backlogs, task boards and charts show everyone the real state of the work every day. Task management means breaking work into tasks, prioritizing them and knowing when each is truly done.

BacklogprioritizedTask boardTo do, Doing, DoneBurndownwork leftReviewmeets Definition of Done

How it works

Common adaptive artifacts

ArtifactWhat it shows
Product backlogAll desired work, ordered by priority
Iteration (sprint) backlogThe items and tasks selected for the current iteration
Task board or Kanban boardEach item's status in columns, for example To do, In progress, Done
Burndown chartWork remaining over time; the line should fall toward zero
Burnup chartWork completed over time against total scope; shows scope changes clearly
Cumulative flow diagramItems in each state over time; widening bands reveal bottlenecks
Velocity chartWork completed per iteration
Definition of Done (DoD)The shared checklist for when an item is complete
Product roadmap and release planWhen groups of features are expected
Information radiatorAny large, visible display of project information, such as a board on the wall

Reading a burndown chart

PatternMeaning
Actual line above the ideal lineBehind plan
Actual line below the ideal lineAhead of plan
Flat line for several daysNo work being completed, or work not being updated
Line goes upScope was added or work was re-estimated upward

Success criteria for a task

A task or story is finished when it meets its acceptance criteria and the team's Definition of Done.

  • Acceptance criteria are specific to one item: what it must do to be accepted, often written as "Given ... when ... then ...".
  • The Definition of Done applies to all items: for example coded, tested, reviewed, documented and integrated.
  • Some teams also use a Definition of Ready: an item is clear and small enough to start.

Prioritizing tasks

TechniqueHow it works
MoSCoWMust have, Should have, Could have, Won't have this time
Business valueHighest value items first
RiskTackle high-risk items early to learn sooner
DependenciesItems others depend on come first
Kano modelClassifies features as basic, performance or delighters
Minimum viable product (MVP)The smallest product that delivers value and lets the team learn

The product owner sets the priority of backlog items; the team breaks items into tasks and decides who does them.

Task management steps

  1. Take the highest priority items into the iteration.
  2. Break each item into tasks.
  3. Team members pull tasks; show them on the board.
  4. Update the board and burndown daily; raise blockers at the standup.
  5. Check each item against its acceptance criteria and the Definition of Done.
  6. Demonstrate completed items at the review; reflect at the retrospective.
Exam tip

A burndown that rises usually means scope was added. A burnup makes this easier to see because it shows total scope as a separate line.

How the exam asks about this

  • "What does MoSCoW stand for?" Must have, Should have, Could have, Won't have.
  • "Which chart shows work remaining in the iteration?" A burndown chart.
  • "When is a user story done?" When it meets its acceptance criteria and the Definition of Done.

What to remember for the exam

  • Artifacts: product and iteration backlogs, task board, burndown, burnup, cumulative flow, Definition of Done.
  • Burndown: work left; burnup: work done against total scope.
  • Acceptance criteria are per item; the Definition of Done applies to all items.
  • MoSCoW: Must, Should, Could, Won't.
  • The product owner prioritizes; the team plans the tasks.
Watch out

Do not mark an item done because the code is written. It must meet the acceptance criteria and the Definition of Done.

Common mistakes

Confusing burndown and burnup. Burndown falls toward zero; burnup rises toward total scope.

Mixing acceptance criteria with the Definition of Done. One is item specific; the other is shared.

Letting the project manager assign every task. Agile teams pull work.

Check yourself

  • What is an information radiator?

    A large, visible display of project information, such as a task board or burndown chart.

  • What is the difference between acceptance criteria and the Definition of Done?

    Acceptance criteria are specific to one item; the Definition of Done is a shared standard for every item.

  • Who prioritizes the product backlog?

    The product owner.

Topic 4 of 4 in Agile Frameworks/Methodologies

Test yourself on Agile Frameworks/Methodologies

The full PMI CAPM question bank has 1,049 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PMI. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.