Risks, Issues, Assumptions, Constraints and Ethics

CAPM essentials: telling risks, issues, assumptions and constraints apart, the logs that hold them, and the four values of the PMI Code of Ethics.

  • 4 min
In a nutshell
  • Risk: may happen. Issue: has happened. Assumption: believed true. Constraint: a limit.
  • Risks go in the risk register; issues in the issue log; assumptions and constraints in the assumption log.
  • Risks can be threats or opportunities.

What it is

Every project works with uncertainty and limits. CAPM expects you to tell four ideas apart: a risk may happen, an issue has happened, an assumption is believed true without proof, and a constraint is a limit you must work within. Each is recorded in its own place so the team can act on it.

The PMI Code of Ethics and Professional Conduct guides how project practitioners behave while they do this work.

Assumptionbelieved trueProves falseRiskmay happenOccursIssuehappening now

How it works

Four terms that look alike

TermMeaningWhere it is recordedExample
RiskAn uncertain event or condition that, if it occurs, has a positive or negative effect on objectivesRisk registerA key supplier might deliver late
IssueA current condition or situation that may affect objectivesIssue logThe supplier has delivered late
AssumptionA factor believed to be true, real or certain without proofAssumption logThe test lab will be available in May
ConstraintA limiting factor on the projectAssumption log, project charter, scope statementThe budget cannot exceed 200,000

Risks can be threats (negative) or opportunities (positive). An issue is handled now; a risk is planned for in advance.

Typical constraints

The classic constraints are scope, schedule and cost, often extended with quality, resources and risk. Changing one usually affects the others. For example, cutting the schedule may need more resources or a smaller scope.

From one to another

  • An assumption that turns out to be false becomes a risk or an issue.
  • A risk that occurs becomes an issue.
  • An issue that cannot be resolved at the team's level may need to be escalated.

A worked example: the team assumes users have the latest browser. Testing shows 30% do not. The assumption was wrong, so the team records an issue in the issue log, assigns an owner, and checks the risk register for other browser related risks.

The PMI Code of Ethics and Professional Conduct

The Code is built on four values:

ValueWhat it means in practice
ResponsibilityTaking ownership of decisions and their consequences; keeping commitments
RespectTreating people and resources with regard; listening to other views
FairnessMaking decisions impartially and objectively; disclosing conflicts of interest
HonestyTelling the truth in communication and conduct

For each value the Code has aspirational standards (what practitioners strive for) and mandatory standards (firm requirements).

Ethics scenarios

ScenarioEthical response
A supplier offers you a gift to win a contractDecline it and follow the organization's policy; disclose the offer
You realize your status report understated a delayCorrect it and report the true status
A friend's company bids on your projectDisclose the conflict of interest and step back from the decision
You are asked to do work you are not qualified forSay so honestly and seek help or training
Exam tip

In ethics questions, choose the answer that is honest, follows policy and makes the situation transparent. Hiding, delaying or "handling it quietly" is almost never right.

How the exam asks about this

  • "A risk has occurred. Where is it now tracked?" In the issue log.
  • "The team believes a vendor will deliver on time but has no proof. What is this?" An assumption.
  • "Which Code of Ethics value covers disclosing a conflict of interest?" Fairness.

What to remember for the exam

  • Risk: may happen. Issue: has happened. Assumption: believed true. Constraint: a limit.
  • Risks go in the risk register; issues in the issue log; assumptions and constraints in the assumption log.
  • Risks can be threats or opportunities.
  • A false assumption can create a risk or an issue.
  • Code of Ethics values: responsibility, respect, fairness, honesty.
Watch out

Do not put a current problem in the risk register and wait. Once it has happened, it is an issue and needs action.

Common mistakes

Treating every risk as negative. Opportunities are risks too.

Calling a budget limit an assumption. A fixed limit is a constraint.

Picking a "smooth it over" answer in ethics questions. Honesty and transparency come first.

Check yourself

  • What is the difference between a risk and an issue?

    A risk is uncertain and may happen in future; an issue is a condition that exists now.

  • Where are assumptions and constraints recorded?

    In the assumption log, with key ones also in the charter and scope statement.

  • What are the four values of the PMI Code of Ethics and Professional Conduct?

    Responsibility, respect, fairness and honesty.

Topic 2 of 6 in Project Management Fundamentals and Core Concepts

Test yourself on Project Management Fundamentals and Core Concepts

The full PMI CAPM question bank has 1,049 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PMI. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.