Predictive, Plan-Based Methodologies · Topic 3 of 3

Predictive Artifacts and Cost and Schedule Variances

CAPM project controls: predictive artifacts, change requests and logs, and earned value basics: PV, EV, AC, CV, SV, CPI and SPI with a worked example.

  • 4 min
  • Includes a diagram
In a nutshell
  • Artifacts: charter, plan and baselines, WBS, schedule, risk register, issue log, change log, traceability matrix, lessons learned.
  • Change requests go through integrated change control before baselines change.
  • CV = EV minus AC; SV = EV minus PV.

What it is

Project controls compare actual performance with the plan and trigger action when they differ. In a predictive project, the team records work in standard artifacts (plans, baselines, registers, logs and reports) and measures performance with earned value figures such as cost variance and schedule variance.

Baselinesscope, schedule, costMeasure actualsVarianceCV and SVChange requestIntegrated change control

How it works

Common predictive artifacts

ArtifactWhat it holds
Project charterAuthorization, objectives, summary milestones and budget
Project management planSubsidiary plans and the scope, schedule and cost baselines
WBS and WBS dictionaryDecomposed scope and the details of each element
Project scheduleActivities, dates and dependencies, often as a Gantt chart
Risk registerIdentified risks, owners and responses
Issue logCurrent issues, owners and status
Change logAll change requests and their status
Requirements traceability matrixLinks each requirement to its source and the deliverable that satisfies it
Lessons learned registerKnowledge gained during the project
Status and performance reportsProgress, variances and forecasts

A Gantt chart shows activities as bars against a timeline. A milestone chart shows only the key dates.

Change requests

A change request is a formal proposal to change a document, deliverable or baseline. It can be a corrective action, a preventive action, a defect repair or an update. Every change request goes through integrated change control: it is analyzed for impact on scope, schedule, cost, quality and risk, then approved or rejected, often by a change control board. Approved changes update the baselines and plans.

Earned value basics

Earned value: schedule variance is EV minus PV and SPI is EV divided by PV; cost variance is EV minus AC and CPI is EV divided by AC. A positive variance or an index above 1 is good; negative or below 1 is bad.

TermMeaning
BAC (budget at completion)The total budget for the work
PV (planned value)The budgeted value of the work scheduled to be done by now
EV (earned value)The budgeted value of the work actually done by now
AC (actual cost)What the work done by now actually cost
MeasureFormulaGood result
Cost variance (CV)EV minus ACPositive: under budget
Schedule variance (SV)EV minus PVPositive: ahead of schedule
Cost performance index (CPI)EV / ACAbove 1: under budget
Schedule performance index (SPI)EV / PVAbove 1: ahead of schedule

In all four formulas, EV comes first. Negative variances, or indices below 1, are bad.

Worked example

A project has BAC = 100,000. By now, the plan says 50,000 of work should be done (PV). The team has finished work worth 40,000 (EV) and spent 45,000 (AC).

MeasureCalculationResultMeaning
CV40,000 minus 45,000minus 5,000Over budget
SV40,000 minus 50,000minus 10,000Behind schedule
CPI40,000 / 45,000about 0.89Getting 89 cents of value per dollar
SPI40,000 / 50,0000.8Progressing at 80% of the planned rate

Percent complete is EV / BAC = 40%.

Exam tip

Memorize "EV first". CV = EV minus AC, SV = EV minus PV, CPI = EV / AC, SPI = EV / PV.

How the exam asks about this

  • "EV = 30,000 and AC = 25,000. What is the CV?" 5,000, under budget.
  • "SPI is 0.9. What does this mean?" The project is behind schedule.
  • "Which document links requirements to the deliverables that satisfy them?" The requirements traceability matrix.

What to remember for the exam

  • Artifacts: charter, plan and baselines, WBS, schedule, risk register, issue log, change log, traceability matrix, lessons learned.
  • Change requests go through integrated change control before baselines change.
  • CV = EV minus AC; SV = EV minus PV.
  • CPI = EV / AC; SPI = EV / PV.
  • Positive variance or index above 1 is good.
Watch out

Actual cost is not progress. A project that has spent half its budget is not half done; earned value shows how much work is actually complete.

Common mistakes

Reversing the formula. CV is EV minus AC, not AC minus EV.

Dividing the wrong way. CPI is EV over AC.

Changing a baseline without an approved change request. Baselines change only through change control.

Check yourself

  • What does a CPI of 1.2 mean?

    The project is getting 1.2 units of value for each unit spent, so it is under budget.

  • What is the formula for schedule variance?

    SV = EV minus PV.

  • What happens to a change request before the baseline is updated?

    It is analyzed and approved through integrated change control, often by a change control board.

Topic 3 of 3 in Predictive, Plan-Based Methodologies

Test yourself on Predictive, Plan-Based Methodologies

The full PMI CAPM question bank has 1,049 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PMI. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.