PRINCE2 Practices · Topic 9 of 9

Progress Reports, Logs and Digital Data

PRINCE2 7 progress products: checkpoint, highlight, exception, end stage, end project and lessons reports, the logs, and digital and data approach.

  • 5 min
In a nutshell
  • Checkpoint: team manager to project manager, time-driven.
  • Highlight: project manager to project board, time-driven.
  • Exception, end stage, end project and lessons reports are event-driven.

What it is

The progress practice uses more management products than any other practice. Each report carries information from one level of management to another at a defined time or event. Two logs in the project log hold day-to-day information, and the digital and data management approach in the PID sets how data and digital tools are used.

Exam questions often name a purpose and ask which product it is, or name a product and ask who produces it and who receives it.

Team managercheckpoint reportProject managerhighlight reportProject boardProject managerexception reportProject boardProject managerend stage reportProject boardBusiness layer

How it works

The reports at a glance

ReportProduced byForPurposeType of control
Checkpoint reportTeam managerProject managerReports the status of a work package at a frequency set in the work package descriptionTime-driven
Highlight reportProject managerProject boardReports the status of the stage at a frequency set by the boardTime-driven
Exception reportProject managerProject boardDescribes an exception, its impact, options and a recommendationEvent-driven
End stage reportProject managerProject boardGives a view of how the stage performed and the project's status, to support the decision on the next stageEvent-driven
End project reportProject managerProject boardReviews how the project performed against the PID, used to evaluate the project and authorise closureEvent-driven
Lessons reportProject managerProject board, then the wider organizationPasses on lessons that could be applied to other projectsEvent-driven

Checkpoint and highlight reports

A checkpoint report covers the period's work on a work package: products completed, products planned next, quality activities, issues and risks, and any tolerance concerns. Its frequency and format are agreed in the work package description.

A highlight report gives the project board a summary of stage status: work done, work planned next, tolerance status, issues and risks, and products completed. It lets the board manage by exception, staying informed without being involved day-to-day.

Exception report

An exception report is produced when a stage or project is forecast to exceed tolerance. It describes the cause, the consequences, the options, the project manager's recommendation and any lessons. It should be produced as soon as the exception is forecast.

End stage and end project reports

The end stage report is produced near the end of each stage (except the final one) during managing a stage boundary. It reviews the stage against its plan, the business case, risks and issues, and is used alongside the next stage plan when the board decides whether to continue.

The end project report is produced during closing a project. It compares the project's performance with the original and current PID, reports on benefits achieved so far, and covers product acceptance and follow-on action recommendations.

Lessons report

A lessons report passes on lessons that could be useful to other projects or to the organization. It can be produced at any time, typically at stage ends, and is produced at project closure. It is the output of the learn from experience principle.

Logs in the project log

LogWhat it holds
Daily logThe project manager's diary: informal issues, required actions, significant events and notes not captured elsewhere
Lessons logLessons from previous projects and lessons found during this project, waiting to be applied or passed on

The daily log is started in starting up a project and used throughout. The lessons log is created at the start too, when lessons from earlier projects are sought.

The digital and data management approach

The digital and data management approach is part of the PID and is new in PRINCE2 7. It describes how the project will manage the data it uses and creates, and how it will use digital systems and tools, for example for reporting, collaboration and record keeping.

Typically coversExample
Data the project will create and useProgress data, financial actuals, risk data
Systems and toolsA shared planning tool and dashboard
Data governance, security and privacyWho can see personal data; retention periods
Data qualityWho checks the reliability of reported figures
ResponsibilitiesProject support maintains the dashboard

A worked example

A software company runs a three stage project to launch a customer portal. Each Friday, team managers send checkpoint reports to the project manager, who sends a monthly highlight report to the project board. The project manager also notes small informal problems in the daily log.

Near the end of stage two, the project manager writes the end stage report and next stage plan. During stage three a forecast overrun triggers an exception report.

At closure, the end project report and a lessons report are sent to the board; the lessons report is passed to the portfolio office. All reports are generated from the planning tool defined in the digital and data management approach.

How the exam asks about this

  • "Which report does a team manager send to the project manager?" The checkpoint report.
  • "Which product does the project board use to stay informed between stage boundaries?" The highlight report.
  • "Where does the project manager record informal issues and actions?" The daily log.

What to remember for the exam

  • Checkpoint: team manager to project manager, time-driven.
  • Highlight: project manager to project board, time-driven.
  • Exception, end stage, end project and lessons reports are event-driven.
  • Daily log and lessons log sit in the project log.
  • The digital and data management approach in the PID covers data and digital tools.
Watch out

The end stage report is not produced for the final stage. At the end of the final stage, the end project report is produced instead.

Common mistakes

Mixing up checkpoint and highlight reports. Checkpoint goes up from team manager; highlight goes up from project manager.

Treating the lessons report as a closure-only product. It can be produced at any time, as well as at closure.

Putting the daily log in the PID. It belongs in the project log.

Check yourself

  • Who receives the highlight report?

    The project board.

  • What does an exception report contain?

    A description of the exception, its cause and impact, the options and the project manager's recommendation.

  • What is the purpose of the lessons log?

    To hold lessons from previous projects and from this project so they can be applied or passed on.

Topic 9 of 9 in PRINCE2 Practices

Test yourself on PRINCE2 Practices

The full PeopleCert PRINCE2 7 Foundation question bank has 564 questions, with timed practice exams and an explanation for every answer.