PRINCE2 Processes · Topic 3 of 4

Controlling a Stage and Managing Product Delivery

PRINCE2 7 processes controlling a stage and managing product delivery: purpose, objectives and context, work packages, checkpoint and highlight reporting.

  • 5 min
In a nutshell
  • Controlling a stage: project manager's day-to-day management of each delivery stage.
  • Controlling a stage starts when the board authorises a stage.
  • Managing product delivery: team manager accepts, executes and delivers work packages.

What it is

Controlling a stage is the project manager's day-to-day management of a stage: assigning work, monitoring it, dealing with issues and risks, and reporting to the project board. Managing product delivery is the team manager's side: accepting, doing and delivering that work.

The two processes are linked by the work package, which formally passes responsibility for work from the project manager to a team manager.

Project managercontrolling a stageauthorise work packageTeam managermanaging product deliveryTeam managercheckpoint reportsProject managerhighlight reportsProject board

How it works

Controlling a stage: purpose

The purpose of controlling a stage is to assign work to be done, monitor that work, deal with issues, report progress to the project board, and take corrective actions to ensure the stage remains within tolerance.

Controlling a stage: objectives

ObjectiveIn plain words
Attention is focused on delivery of the stage's productsNo uncontrolled change or diverted effort
Risks and issues are kept under controlCaptured, assessed and responded to
The business case is kept under reviewChanges in cost, time or benefit are watched
The agreed products for the stage are delivered to the stated quality, within cost, effort and time agreedAnd ultimately support the planned benefits
The project management team is focused on delivery within tolerancesExceptions are raised when forecast

Controlling a stage: context

Controlling a stage begins after the project board authorises a stage, and runs until the end of that stage. It is used for every delivery stage; the initiation stage is managed through initiating a project.

The project manager runs a cycle of work and control, and escalates if stage tolerance is forecast to be exceeded.

Authorise work packagesReview work package statusReceive completed work packagesReview stage statusReport highlightsReview stage statusCapture and examine issues and risksTake corrective action or escalate
SituationProject manager action
Work within stage toleranceTake corrective action and carry on
Stage forecast to exceed toleranceEscalate with an exception report to the board
Stage nearly completeMove into managing a stage boundary
Final stage nearly completeMove into closing a project

Managing product delivery: purpose

The purpose of managing product delivery is to control the link between the project manager and the team manager(s), by agreeing the requirements for acceptance, execution and delivery of work.

Managing product delivery: objectives

ObjectiveIn plain words
Work on products allocated to the team is authorised and agreedThrough the work package
Team managers, team members and suppliers are clear about what is to be produced and the expected effort, cost and timescalesEveryone understands the work
The planned products are delivered to expectations and within toleranceQuality criteria met
Accurate progress information is provided to the project manager at an agreed frequencyCheckpoint reports

Managing product delivery: context

Managing product delivery is carried out by the team manager. It has three broad parts: accept a work package, execute a work package, and deliver a work package.

Accept a work packageExecute a work packageDeliver a work package

The team manager may produce a team plan, keeps the quality register updated for quality checks, sends checkpoint reports, and raises issues if the work package is forecast to exceed tolerance. The specialist teams may use any delivery approach, such as iterative-incremental sprints, inside the work package.

Managing product delivery is especially useful when the team is from an external supplier that does not use PRINCE2. The work package gives the project manager control without dictating how the supplier works.

A worked example

A retailer's warehouse automation project is in stage three. The project manager authorises a work package to the integrator's team manager, describing the conveyor control software, its product descriptions, tolerances of plus or minus one week and fortnightly checkpoint reports.

The team manager accepts it, builds a team plan using two week iterations, and reports progress in checkpoint reports. When a test shows an off-specification, the team manager raises an issue. The project manager handles it within stage tolerance and reports it in the next highlight report.

How the exam asks about this

  • "Which process includes assigning work, monitoring it, dealing with issues and reporting progress to the project board?" Controlling a stage.
  • "What is the purpose of managing product delivery?" To control the link between project manager and team manager by agreeing requirements for acceptance, execution and delivery of work.
  • "Who carries out managing product delivery?" The team manager.

What to remember for the exam

  • Controlling a stage: project manager's day-to-day management of each delivery stage.
  • Controlling a stage starts when the board authorises a stage.
  • Managing product delivery: team manager accepts, executes and delivers work packages.
  • The work package is the formal link between the two processes.
  • Checkpoint reports go to the project manager; highlight reports go to the board.
Watch out

Controlling a stage takes corrective action only within tolerance. Once stage tolerance is forecast to be exceeded, the project manager must escalate.

Common mistakes

Thinking the project manager directs specialists directly. Work is passed through work packages to team managers.

Forcing PRINCE2 onto supplier teams. Managing product delivery only requires agreement on the work package, not that suppliers use PRINCE2.

Running controlling a stage for initiation. The initiation stage is managed through initiating a project.

Check yourself

  • What links controlling a stage and managing product delivery?

    The work package, authorised by the project manager and accepted by the team manager.

  • What are the three parts of managing product delivery?

    Accept a work package, execute a work package and deliver a work package.

  • What does the project manager do when stage tolerance is forecast to be exceeded?

    Escalates to the project board with an exception report.

Topic 3 of 4 in PRINCE2 Processes

Test yourself on PRINCE2 Processes

The full PeopleCert PRINCE2 7 Foundation question bank has 564 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PeopleCert. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.