PRINCE2 Practices · Topic 1 of 9

The PID and the Project Log

The PRINCE2 7 PID and project log: their purpose, the management approaches inside the PID, and the registers and logs held within the project log.

  • 5 min
In a nutshell
  • PID defines the project and is the baseline for managing it.
  • The PID holds the business case, team structure, role descriptions, project plan, controls, tailoring and the management approaches.
  • The project log holds the daily log, issue, risk, quality and product registers and the lessons log.

What it is

PRINCE2 7 groups many management products into two umbrella products. The project initiation documentation (PID) holds the information that defines the project and how it will be managed. The project log holds the registers and logs used to record day-to-day information.

Knowing which product sits inside which umbrella is one of the most tested skills in the exam. Many questions simply ask where a piece of information is recorded.

PIDhow the project is defined and managedBaseline for the projectProject logregisters and logsDay to day records

How it works

The PID

The purpose of the PID is to define the project, so that it forms the basis for its management and an assessment of its overall success. It gives the project board what it needs to decide whether to authorise the project, and it is the baseline the project is managed against.

The PID is produced in initiating a project, approved by the project board in directing a project, and updated at each stage boundary as needed. At closure it is used to compare what was delivered with what was planned.

PID componentWhat it holds
Project definition and approachObjectives, scope, constraints, the chosen delivery approach
Business caseThe justification for the project
Project management team structureWho is on the project board and in other roles
Role descriptionsResponsibilities for each role
Project planThe high-level plan for the whole project
Project controlsStages, tolerances, reporting and escalation arrangements
TailoringHow PRINCE2 is adapted for this project
Management approachesHow each area of management will be handled

The management approaches inside the PID

PRINCE2 7 uses the word approach for these (never "strategy"). Each approach is linked to the practice or element that uses it.

Management approachLinked toPurpose in a phrase
Benefits management approachBusiness caseHow benefits will be measured and confirmed
Sustainability management approachBusiness caseHow sustainability targets are set and managed
Commercial management approachOrganizingHow supplier and commercial relationships are managed
Change management approachPeopleHow the business change will be adopted
Communication management approachPeopleHow and how often stakeholders are communicated with
Quality management approachQualityHow quality is planned, controlled and assured
Risk management approachRiskHow risk is identified, assessed and controlled
Issue management approachIssuesHow issues and changes are handled
Digital and data management approachProgressHow data and digital tools are managed and used

The project log

The purpose of the project log is to record the information the project needs to manage itself day-to-day. It is started in starting up a project, where the daily log and lessons log are first needed, and the registers are set up in initiating a project. It is then maintained throughout.

Within the project logWhat it recordsMain practice
Daily logThe project manager's diary: informal issues, actions, eventsProgress
Issue registerIssues being managed formallyIssues
Lessons logLessons from previous projects and this oneProgress
Product registerThe products of the project and their statusQuality
Quality registerQuality activities planned and carried outQuality
Risk registerIdentified risks and their managementRisk
Project logDaily logProject logIssue registerProject logLessons logProject logProduct registerProject logQuality registerProject logRisk register

Baselines, records and reports

Management products come in three kinds.

Baselines (such as the PID, business case, plans and product descriptions) are approved and change only through change control. Records in the project log are dynamic and updated constantly.

Reports (such as highlight, end stage and issue reports) give a snapshot at a point in time.

A worked example

A charity's project manager is asked three questions by the executive. "How will we know if the new donor app increased donations?" The answer is in the benefits management approach in the PID.

"Has anyone raised the payment provider delay formally?" The answer is in the issue register within the project log.

"Where did we note the supplier's warning about app store approval times?" If it was treated informally, it is in the daily log.

How the exam asks about this

  • "What is the purpose of the PID?" To define the project, forming the basis for its management and for assessing its overall success.
  • "Which is part of the project log?" The risk register (or daily log, issue register, lessons log, quality register, product register). Not the business case.
  • "Where are management approaches documented?" In the PID.

What to remember for the exam

  • PID defines the project and is the baseline for managing it.
  • The PID holds the business case, team structure, role descriptions, project plan, controls, tailoring and the management approaches.
  • The project log holds the daily log, issue, risk, quality and product registers and the lessons log.
  • PRINCE2 7 uses "approach", never "strategy".
  • Baselines change only through change control; records are updated continuously.
Watch out

The business case and project plan are part of the PID, not the project log. Registers and logs are never part of the PID.

Common mistakes

Treating the PID as a one-time document. It is updated at stage boundaries and used at closure to assess success.

Using older terms. "Risk management strategy" and "configuration item records" are not PRINCE2 7 terms; use risk management approach and product register.

Putting the daily log in the PID. The daily log is part of the project log.

Check yourself

  • Which management product contains the risk register?

    The project log.

  • When is the PID created and approved?

    It is created in initiating a project and approved by the project board when it authorises the project.

  • Which approach in the PID explains how benefits will be measured?

    The benefits management approach.

Topic 1 of 9 in PRINCE2 Practices

Test yourself on PRINCE2 Practices

The full PeopleCert PRINCE2 7 Foundation question bank has 564 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PeopleCert. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.