Projects and PRINCE2 Key Concepts · Topic 2 of 2

Why Project Management and the Benefits of PRINCE2

Why organizations use project management, the challenges PRINCE2 addresses, the five project characteristics, project context and the benefits of PRINCE2.

  • 5 min
In a nutshell
  • Projects introduce change; business as usual keeps things running.
  • Five characteristics: change, temporary, cross-functional, unique, uncertainty.
  • Project context covers organizations, programmes and portfolios, commercial relationships, sector and scale.

What it is

Organizations run two kinds of work: business as usual, which keeps things running, and projects, which introduce change. Projects need a different style of management because they are temporary, unique and uncertain.

This page explains why organizations use project management, the common challenges PRINCE2 is designed to address, the five characteristics that separate a project from business as usual, how the project's context matters, and what PRINCE2 offers in return.

Need for changeProjecttemporary and uniqueProject managementControlled delivery of outputsOutcomes and benefits

How it works

Why project management is used

Organizations keep changing to respond to competition, regulation, technology and customer expectations. Change carries risk, and business as usual structures are not designed to manage it.

Project management gives the change a dedicated, temporary structure with clear decision making, control of the investment and a focus on delivering what was agreed. It lets the organization decide whether the change is worth pursuing and keep checking that it still is.

Challenges PRINCE2 is designed to address

Projects commonly struggle for a familiar set of reasons. PRINCE2 7 groups its response to them into the method's elements.

Common challengeHow PRINCE2 responds
Unclear or changing justificationBusiness case kept up to date throughout
Nobody sure who decides whatDefined roles, responsibilities and relationships
Plans that are unrealistic or too detailed too earlyPlanning horizons and management stages
Senior managers overloaded or not involvedManage by exception with clear tolerances
Products delivered that users do not acceptFocus on products with agreed quality criteria
Mistakes repeated from earlier projectsLearn from experience
Stakeholders and the people affected not engagedThe people element, engagement and communication

You do not need a numbered list of challenges for the exam. Be ready to recognise that each PRINCE2 principle and practice exists to fix a known way projects go wrong.

The five characteristics of a project

CharacteristicMeaning
ChangeProjects are the means by which organizations introduce change
TemporaryA project has a defined start and end; business as usual continues indefinitely
Cross-functionalA project brings together people with different skills, often from different organizations
UniqueEvery project is different in some way, even if similar to earlier ones
UncertaintyBecause of the other four, projects carry more risk than business as usual

Exam distractors often offer "repetitive" or "permanent", which describe business as usual instead.

Projects in context

No project runs in isolation. The project context is the setting that shapes how the method is applied, and it is one of the five integrated elements.

Context includes the organization or organizations involved, whether the project is standalone or part of a programme or portfolio, whether there is a commercial relationship between a customer and suppliers, the sector and any regulation, and the project's scale and complexity. A large multi-supplier infrastructure project and a small internal process change will both use PRINCE2, but in very different ways.

Organization and sectorProject contextTailoring decisionsHow PRINCE2 is appliedProgramme or portfolioProject context

Features and benefits of PRINCE2

FeatureBenefit to the organization
Can be applied to any type, size and sector of projectOne method across the organization
Widely recognised and understoodA common vocabulary for customers, suppliers and staff
Can be used alongside specialist and delivery modelsWorks with agile, engineering or other specialist approaches
Explicit roles and responsibilitiesEveryone knows what is expected of them and who decides
Product focusClarity on what will be delivered and to what quality
Manage by exceptionEfficient use of senior management time
Continued business justificationInvestment stopped when the project is no longer worthwhile
Learning built inEach project improves the next

A worked example

A hospital trust is replacing its patient booking system. The work is temporary, involves IT, clinical and administrative staff, is new to this trust, and has uncertainty about data migration: all five characteristics are present.

It is part of a wider digital programme, a supplier is under contract, and patient data is regulated, so the project context is complex. The trust chooses PRINCE2 because the supplier already uses the same vocabulary and the programme board wants decisions only when tolerances are threatened.

How the exam asks about this

  • "Which is a characteristic of a project?" Uncertainty (or change, temporary, cross-functional, unique). Not "repeatable" or "permanent".
  • "Why does a project carry more risk than business as usual?" Because it introduces change, is temporary, unique and cross-functional, so its outcome is uncertain.
  • "Which is a benefit of PRINCE2?" For example, it gives a common vocabulary, or manage by exception makes efficient use of management time.

What to remember for the exam

  • Projects introduce change; business as usual keeps things running.
  • Five characteristics: change, temporary, cross-functional, unique, uncertainty.
  • Project context covers organizations, programmes and portfolios, commercial relationships, sector and scale.
  • PRINCE2 can be applied to any project and combined with specialist models.
  • Each principle and practice answers a known cause of project problems.
Watch out

"Uncertainty" is a characteristic caused by the other four. Do not pick "risk free" or "repetitive" as a project characteristic.

Common mistakes

Treating the context as optional. Project context is one of the five integrated elements and drives tailoring.

Thinking PRINCE2 replaces specialist methods. It manages the project and works alongside specialist delivery approaches.

Calling a recurring process a project. Repeated, ongoing work is business as usual, not a project.

Check yourself

  • What are the five characteristics of a project?

    Change, temporary, cross-functional, unique and uncertainty.

  • Why must a project's context be understood?

    Because the organization, commercial setting, sector and scale all shape how PRINCE2 is tailored and applied.

  • How does manage by exception benefit an organization?

    Senior managers are only involved when tolerances are forecast to be exceeded, which saves their time.

Topic 2 of 2 in Projects and PRINCE2 Key Concepts

Test yourself on Projects and PRINCE2 Key Concepts

The full PeopleCert PRINCE2 7 Foundation question bank has 564 questions, with timed practice exams and an explanation for every answer.

This study guide is independent and is not affiliated with, endorsed by, or sponsored by PeopleCert. Vendor names, certification names and exam codes are trademarks of their respective owners and are used for identification only.